Chariot Construction can provide high-quality, fully trained labour to carry out a wide range of tasks on high-voltage electricity transmission systems including:-

  • Erecting
  • Re-wiring
  • Surveying
  • Strengthening
  • Step-bolting
  • Safety Climbing Devices

Since 2004 we have been involved with a wide variety of projects, from the large-scale to the very small. Our case studies illustrate our diversity.

Year
Location Summary
Value
2013
Chinchilla, QLD, Australia Assembly & erection of transmission towers
AUD $1m
2013
Mangoola Assembly & erection of 500kV transmission towers for Xstrata
AUD $3m
2013
Hopes Down 4 Assembly & erection of transmission towers with Downer Engineering and Rio Tinto
AUD $3m
2010-12
North Island Grid Upgrade Project, New Zealand Upgrading transmission capacity into Auckland, dismantling of old 100kV line and erection of 185km length of 400kV towers.
NZD $3m
2009
Enterprise Power Services, UK Various overhead line works at sites across the UK including Rugeley and the Sundon-Westoning line.
GBP £60k
2008
Balfour Beatty, UK Quality Assurance Inspection of Rapid Rail Systems.
GBP £50k
2007
Olympic Village, UK Erection of six temporary L8 towers (60ft extensions on all towers) to enable tunn elling project to lay underground cables.
GBP £107k
2006
Indian Queens to Exeter, UK Fully re-insulated and re-spaced 275kV line.
GBP £620k
2006
M1 Motorway, Luton, UK Erected new L7 towers, re-wired as part of the M1 widening project.
GBP £180k
2005
Alps, Italy/Switzerland Erected new 400kV line over top of the Alps mountain range across the Italian/Swiss border using helicopter and derrick.
GBP £250k